7/13-Area Road and Bridge Work

MoDOT/Southwest Road Report for Monday, July 16

(Weather and/or work scheduling conflicts could postpone the work.)

 

RATE OUR WORK ZONES

 

LEGEND

 

Work zone – Road Closed

 Work zone – Expect Delays

 Work zone – Possible Delays

 Future Work zone

Barry County

US 60 – BARRY COUNTY – Expect Delays

INTERSECTION IMPROVEMENTS
Scheduled from 05-JUL-2018 to 24-SEP-2018.
Road work begins .14 MILES BEFORE MO 37 S.
Work will be done around the clock, on weekdays only.

State Route 37 – BARRY COUNTY – Expect Delays

INTERSECTION IMPROVEMENTS
Scheduled from 05-JUL-2018 to 24-SEP-2018.
Road work begins .06 MILES BEFORE US 60 E.
Work will be done around the clock, on weekdays only.

State Route 86 – BARRY COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 11-JUL-2018 to 17-JUL-2018.
Road work begins 2.28 MILES AFTER RT H S.
Work will be done around the clock, on weekdays only.

Barton County

State Route 126 – BARTON COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .16 MILES AFTER US 71 N.
Work will be done around the clock, on weekdays only.

State Route 37 – BARTON COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .13 MILES AFTER US 160 W.
Work will be done around the clock, on weekdays only.

 

Bates County

State Route AA – BATES COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Road closure begins 1.04 MILES AFTER RT E E.
Scheduled from 18-JUN-2018 to 20-AUG-2018.

State Route V – BATES COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Road closure begins 1.98 MILES AFTER MO 52 E.
Scheduled from 06-JUN-2018 to 14-SEP-2018.

Interstate 49 – BATES COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 16-JUL-2018 to 17-JUL-2018.
Road work begins 1.9 MILES AFTER RT A W.
Work will be done around the clock, on weekdays only.

State Route 52 – BATES COUNTY – Expect Delays

PAVEMENT REPAIR
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .01 MILES AFTER RT BB N.
Work will be done around the clock, on weekdays only.

State Route BB – BATES COUNTY – Expect Delays

PAVEMENT REPAIR
Scheduled from 09-JUL-2018 to 18-JUL-2018.
Road work begins .18 MILES AFTER MO 18 W.
Work will be done around the clock, on weekdays only.

State Route J – BATES COUNTY – Expect Delays

PAVEMENT REPAIR
Scheduled from 12-JUL-2018 to 16-JUL-2018.
Road work begins .46 MILES AFTER MO 52 W.
Work will be done around the clock, on weekdays only.

State Route B – BATES COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 16-JUL-2018 to 26-JUL-2018.
Road work begins 1.79 MILES BEFORE RT N N.
Work will be done around the clock, on weekdays only.

 

Benton County

No traffic impacts

Cedar County

State Route O  – CEDAR COUNTY – Expect Delays

PAVEMENT REPAIR
Scheduled from 12-JUL-2018 to 16-JUL-2018.
Road work begins 3.47 MILES BEFORE RT B W.
Work will be done around the clock, on weekdays only.

State Route 32 – CEDAR COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 16-JUL-2018 to 26-JUL-2018.
Road work begins 2.89 MILES BEFORE RT CC E.
Work will be done around the clock, on weekdays only.

Christian County

State Route 125 – CHRISTIAN COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Road closure begins 3.72 MILES AFTER RT UU N.
Scheduled from 07-MAY-2018 to 31-AUG-2018.

State Route 14 – CHRISTIAN COUNTY – Expect Delays

PATCHING DRIVE SURFACE
Scheduled from 09-JUL-2018 to 26-JUL-2018.
Road work begins 1.09 MILES AFTER MO 125 S.
Work will be done around the clock, on weekdays only.

State Route K  – CHRISTIAN COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 28-MAY-2018 to 20-JUL-2018.
Road work begins .02 MILES AFTER RT P N.
Work will be done around the clock, on weekdays only.

Dade County

No traffic impacts

 

Dallas County

No traffic impacts

Greene County

US 65 South – GREENE COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Scheduled from 14-JUL-2018 to 01-SEP-2018.
Road work begins .3 MILES BEFORE IS 44 W.
Work will be done around the clock, on weekdays and Saturdays.

Ramp IS44E TO US65N North – GREENE COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Scheduled from 14-JUL-2018 to 01-SEP-2018.
Road work begins AT IS 44 E.
Work will be done around the clock, on weekdays and Saturdays.

Ramp IS44W TO US65S South – GREENE COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Scheduled from 14-JUL-2018 to 21-AUG-2018.
Road work begins AT IS 44 W.
Work will be done around the clock, on weekdays and Saturdays.

Ramp US65S TO IS44E East – GREENE COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Scheduled from 14-JUL-2018 to 21-AUG-2018.
Road work begins AT US 65 S.
Work will be done around the clock, on weekdays and Saturdays.

Outer Road 65 – GREENE COUNTY – CLOSED

NEW PAVEMENT CONSTRUCTION
Road closure begins LESS THAN .01 MILES AFTER CST CHERRY ST E.
Scheduled from 10-JUL-2018 to 10-AUG-2018.

Interstate 44 – GREENE COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 15-JUL-2018 to 07-DEC-2018.
Road work begins 2.26 MILES AFTER RT PP S.
Work will be done around the clock, on weekdays and Saturdays.

US 60 – GREENE COUNTY – Expect Delays

NEW PAVEMENT CONSTRUCTION
Scheduled from 20-MAR-2018 to 27-JUL-2018.
Road work begins .08 MILES AFTER CST SCHOOLCRAFT FWY S.
Work will be done around the clock, 7 days a week.

US 60 – GREENE COUNTY – Expect Delays

SHOULDER WORK
Scheduled from 23-APR-2018 to 31-JUL-2018.
Road work begins .09 MILES AFTER CST SCHOOLCRAFT FWY S.
Work will be done around the clock, on weekdays only.

US 65 – GREENE COUNTY – Expect Delays

SHOULDER WORK
Scheduled from 09-JUL-2018 to 20-JUL-2018.
Road work begins .1 MILES AFTER CST SCHOOLCRAFT FWY S.
Work will be done around the clock, on weekdays only.

State Route 360 – GREENE COUNTY – Expect Delays

NEW PAVEMENT CONSTRUCTION
Scheduled from 20-MAR-2018 to 27-JUL-2018.
Road work begins .06 MILES AFTER US 60 W.
Work will be done around the clock, 7 days a week.

Henry County

State Route 13 – HENRY COUNTY – Expect Delays

SHOULDER WORK
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins 1.46 MILES AFTER MO 52 E.
Work will be done around the clock, on weekdays only.

State Route 18 – HENRY COUNTY – Delays Possible

BRIDGE MAINTENANCE
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins 1.63 MILES BEFORE CRD NW 40TH RD E.
Work will be done around the clock, on weekdays only.

State Route PP – HENRY COUNTY – Delays Possible

BRIDGE MAINTENANCE
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins 1.75 MILES BEFORE RT C E.
Work will be done around the clock, on weekdays only.

Hickory County

No traffic impacts

Jasper County

Ramp MO96 TO IS49N North – JASPER COUNTY – CLOSED

CONCRETE OVERLAY
Road closure begins AT MO 96 E.
Scheduled from 24-MAY-2018 to 15-AUG-2018.

Interstate 49 – JASPER COUNTY – Expect Delays

CONCRETE OVERLAY
Scheduled from 30-APR-2018 to 15-DEC-2018.
Road work begins LESS THAN .01 MILES AFTER CRD CIVIL WAR RD N.
Work will be done around the clock, 7 days a week.

State Route 43 – JASPER COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 04-JUN-2018 to 01-AUG-2018.
Road work begins LESS THAN .01 MILES BEFORE CST HEARNES BLVD S.
Work will be done around the clock, on weekdays only.

State Route 66 – JASPER COUNTY – Expect Delays

SIDEWALK/ADA IMPROVEMENTS
Scheduled from 06-JUN-2018 to 04-SEP-2018.
Road work begins AT MO 249 S.
Work will be done around the clock, on weekdays and Saturdays.

State Route 171 – JASPER COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 16-JUL-2018 to 26-JUL-2018.
Road work begins 2.04 MILES BEFORE RT HH E.
Work will be done around the clock, on weekdays only.

State Route 171 – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .09 MILES AFTER MO 43 S.
Work will be done around the clock, on weekdays only.

State Route 37 – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .2 MILES AFTER LP 44 E.
Work will be done around the clock, on weekdays only.

State Route 43 – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .16 MILES BEFORE RT H W.
Work will be done around the clock, on weekdays only.

State Route 96 – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .03 MILES AFTER RT YY W.
Work will be done around the clock, on weekdays only.

State Route AA – JASPER COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 20-JUN-2018 to 01-AUG-2018.
Road work begins .03 MILES AFTER LP 44 W.
Work will be done around the clock, on weekdays only.

State Route FF – JASPER COUNTY – Expect Delays

SIDEWALK/ADA IMPROVEMENTS
Scheduled from 05-JUN-2018 to 31-JUL-2019.
Road work begins .01 MILES AFTER LP 49 S.
Work will be done around the clock, on weekdays only.

State Route HH – JASPER COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 20-JUN-2018 to 01-AUG-2018.
Road work begins .03 MILES AFTER MO 171 S.
Work will be done around the clock, on weekdays only.

State Route TT – JASPER COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 11-JUN-2018 to 01-AUG-2018.
Road work begins AT CST NEWMAN RD W.
Work will be done around the clock, on weekdays only.

State Route U – JASPER COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 10-JUL-2018 to 03-AUG-2018.
Road work begins .02 MILES BEFORE IS 44 E.
Work will be done around the clock, on weekdays only.

State Route VV – JASPER COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 20-JUN-2018 to 01-AUG-2018.
Road work begins LESS THAN .01 MILES AFTER CRD E ZORA ST W.
Work will be done around the clock, on weekdays only.

State Route Z – JASPER COUNTY – Expect Delays

PERMIT OR UTILITY WORK
Scheduled from 12-JUN-2018 to 01-AUG-2018.
Road work begins .01 MILES AFTER RT JJ N.
Work will be done around the clock, on weekdays only.

State Route BB – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .16 MILES AFTER MO 96 W.
Work will be done around the clock, on weekdays only.

State Route C – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .11 MILES AFTER MO 37 N.
Work will be done around the clock, on weekdays only.

State Route D – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .07 MILES BEFORE CST CHURCH ST E.
Work will be done around the clock, on weekdays only.

State Route D  – JASPER COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 16-JUL-2018 to 26-JUL-2018.
Road work begins .96 MILES BEFORE CST IVY RD W.
Work will be done around the clock, on weekdays only.

State Route E – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .03 MILES AFTER CRD GUM RD E.
Work will be done around the clock, on weekdays only.

State Route F – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins LESS THAN .01 MILES AFTER CRD GUM RD W.
Work will be done around the clock, on weekdays only.

State Route H – JASPER COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .05 MILES BEFORE MO 43 S.
Work will be done around the clock, on weekdays only.

State Route M – JASPER COUNTY – Expect Delays

MILLING/RESURFACING WORK
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins LESS THAN .01 MILES AFTER MO 171 N.
Work will be done around the clock, on weekdays only.

Lawrence County 

Interstate 44 – LAWRENCE COUNTY – Expect Delays

SURVEYING
Scheduled from 13-JUL-2018 to 01-SEP-2018.
Road work begins .14 MILES AFTER RT O S.
Work will be done around the clock, 7 days a week.

Interstate 44  – LAWRENCE COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 09-JUL-2018 to 20-JUL-2018.
Road work begins 1.14 MILES AFTER MO 39 N.
Work will be done around the clock, on weekdays only.

State Route 266 – LAWRENCE COUNTY – Expect Delays

BRIDGE MAINTENANCE
Scheduled from 16-JUL-2018 to 26-JUL-2018.
Road work begins .28 MILES BEFORE CST MAIN ST E.
Work will be done around the clock, on weekdays only.

State Route 96 – LAWRENCE COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .21 MILES AFTER RT AA N.
Work will be done around the clock, on weekdays only.

State Route C – LAWRENCE COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .11 MILES AFTER RT AA N.
Work will be done around the clock, on weekdays only.

State Route F – LAWRENCE COUNTY – Expect Delays

MOWING
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .96 MILES BEFORE RT U N.
Work will be done around the clock, on weekdays only.

State Route O – LAWRENCE COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins LESS THAN .01 MILES AFTER IS 44 W.
Work will be done around the clock, on weekdays only.

McDonald County

State Route E – MCDONALD COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Road closure begins 5.18 MILES AFTER MO 76 E.
Scheduled from 07-MAY-2018 to 03-SEP-2018.

State Route 43 – MCDONALD COUNTY – Expect Delays

CHIP SEAL OVERLAY
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .18 MILES BEFORE RT B E.
Work will be done around the clock, on weekdays only.

Newton County

Interstate 44 – NEWTON COUNTY – Expect Delays

BRIDGE RECONSTRUCTION
Scheduled from 16-JAN-2018 to 19-NOV-2018.
Road work begins .13 MILES AFTER LP 49 N.
Work will be done around the clock, 7 days a week.

Interstate 44 – NEWTON COUNTY – Expect Delays

SURVEYING
Scheduled from 13-JUL-2018 to 01-SEP-2018.
Road work begins 1 MILE AFTER LP 49 S.
Work will be done around the clock, 7 days a week.

State Route 86 – NEWTON COUNTY – Expect Delays

SIDEWALK/ADA IMPROVEMENTS
Scheduled from 07-MAY-2018 to 20-JUL-2018.
Road work begins AT CST HARMONY ST E.
Work will be done around the clock, on weekdays only.

State Route 86 – NEWTON COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 10-JUN-2018 to 01-SEP-2018.
Road work begins .17 MILES AFTER MO 175 N.
Work will be done around the clock, on weekdays and Saturdays.

State Route 43 – NEWTON COUNTY – Expect Delays

CHIP SEAL OVERLAY
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins .17 MILES AFTER BU 60 W.
Work will be done around the clock, on weekdays only.

State Route D – NEWTON COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 04-JUN-2018 to 01-SEP-2018.
Road work begins LESS THAN .01 MILES BEFORE CST DONIPHAN DR N.
Work will be done around the clock, on weekdays and Saturdays.

State Route K – NEWTON COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 04-JUN-2018 to 01-SEP-2018.
Road work begins AT MO 86 E.
Work will be done around the clock, on weekdays and Saturdays.

Polk County

State Route TT – POLK COUNTY – Expect Delays

PATCHING DRIVE SURFACE
Scheduled from 11-JUL-2018 to 19-JUL-2018.
Road work begins 3.6 MILES BEFORE MO 64 W.
Work will be done around the clock, on weekdays only.

State Route YY – POLK COUNTY – Expect Delays

PATCHING DRIVE SURFACE
Scheduled from 12-JUL-2018 to 19-JUL-2018.
Road work begins 2.17 MILES BEFORE RT H S.
Work will be done around the clock, on weekdays only.

St. Clair County

State Route 13 – ST. CLAIR COUNTY – Expect Delays

MILLING/RESURFACING WORK
Scheduled from 12-JUN-2018 to 02-AUG-2018.
Road work begins 1.48 MILES BEFORE RT A E.
Work will be done around the clock, on weekdays and Saturdays.

Stone County

State Route V – STONE COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Road closure begins 4.33 MILES AFTER MO 176 E.
Scheduled from 01-MAY-2018 to 31-AUG-2018.

State Route 76 – STONE COUNTY – Expect Delays

PERMIT OR UTILITY WORK
Scheduled from 11-JUN-2018 to 15-NOV-2018.
Road work begins .82 MILES AFTER CST BUSINESS 13 S.
Work will be done around the clock, on weekdays only.

State Route A – STONE COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 28-MAY-2018 to 20-JUL-2018.
Road work begins LESS THAN .01 MILES AFTER RT K N.
Work will be done around the clock, on weekdays only.

State Route K – STONE COUNTY – Expect Delays

RESURFACING PAVEMENT
Scheduled from 28-MAY-2018 to 20-JUL-2018.
Road work begins AT RT A E.
Work will be done around the clock, on weekdays only.

State Route H – STONE COUNTY – Expect Delays

CHIP SEAL OVERLAY
Scheduled from 16-JUL-2018 to 16-JUL-2018.
Road work begins .02 MILES AFTER MO 39 N.
Work will be done around the clock, on weekdays only.

Taney County 

State Route 76 – TANEY COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Road closure begins 5.13 MILES BEFORE MO 125 S.
Scheduled from 05-JUL-2018 to 31-DEC-2018.

State Route FF – TANEY COUNTY – Expect Delays

PATCHING DRIVE SURFACE
Scheduled from 16-JUL-2018 to 16-JUL-2018.
Road work begins .05 MILES AFTER MO 76 W.
Work will be done around the clock, on weekdays only.

Vernon County

State Route M  – VERNON COUNTY – Expect Delays

PAVEMENT REPAIR
Scheduled from 16-JUL-2018 to 19-JUL-2018.
Road work begins 1.98 MILES AFTER RT OO W.
Work will be done around the clock, on weekdays only.

Webster County

State Route KK – WEBSTER COUNTY – CLOSED

BRIDGE RECONSTRUCTION
Road closure begins 4.68 MILES BEFORE RT A S.
Scheduled from 29-MAY-2018 to 03-AUG-2018.

State Route EE – WEBSTER COUNTY – Expect Delays

PATCHING DRIVE SURFACE
Scheduled from 16-JUL-2018 to 02-AUG-2018.
Road work begins AT MO 38 E.
Work will be done around the clock, on weekdays only.

State Route P – WEBSTER COUNTY – Expect Delays

PAVEMENT REPAIR
Scheduled from 16-JUL-2018 to 25-JUL-2018.
Road work begins AT MO 38 E.
Work will be done around the clock, on weekdays only.

State Route W – WEBSTER COUNTY – Expect Delays

PATCHING DRIVE SURFACE
Scheduled from 16-JUL-2018 to 02-AUG-2018.
Road work begins AT RT Y E.
Work will be done around the clock, on weekdays only.

 END

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)

(Follow MoDOT’s Southwest District: Facebook | Twitter |Instagram |YouTube)

(For timely traffic information in the Springfield area, visitwww.ozarkstraffic.com)